Stay up to date as the plans progress
11th May 2026
Works expected this week:
- Work will begin to fit out the interior of the temporary canteen.
- Waste will continue to be moved from the site to the skip area. Skip exchange is planned for midday on Wednesday.
- Building of the timber hoarding will begin on Monday.
- Root protection will begin on Monday.
- Cleaning and removal of the below-ground tank will begin on Wednesday.
- The site will be monitored by an ecologist to assess the presence of bats from sunset on Thursday to sunrise on Friday.
- Deliveries are likely to take place once or twice a day.
4th May 2026
Works expected this week:
- The temporary works canteen will be built and fitted out.
- Waste will be moved from the build site to the skip, avoiding busy periods.
- The wall at the rear of the site will be dismantled to allow for vehicle access. This will be
rebuilt using the existing bricks following completion of the works. - Timber hoardings will be built and painted.
- There are likely to be one or two deliveries each day.

Today Darwin welcomed the first contractors on site, signalling the beginning of the Pump House building project.
The lead contractor, Barnes Construction, will have a permanent presence on site for the next year in order to coordinate the different teams and act as a point of contact for the College.
- Prepare a contractor welfare area within the basement of 1 Newnham Terrace
- Construct a flat-pack site office and run temporary services such as electricity to it
- Remove the garden door from 1 Newnham Terrace garden door, replacing it with a temporary works door
- Erect heras fencing around the work site and at the blue gates entrance
- Clear the tank room (under the Dining Hall) and complete structural support works.
27th February 2026
Final preparations have been made to the main site by the College teams ahead of the contractors’ expected arrival on site at the end of March.
A provisional schedule of works and impact to the main site can be seen below. This is wholly dependant on the progress of works and is subject to change. An updated version will be posted every month.
16th January 2026
In preparation for the building works to begin by the river, trees will be cleared next week behind 11 and 12 Newnham Terrace, as well as on the islands to provide clearance for punting.
29th September 2025
Owing to a delay in receiving the permissions required from the Environment Agency, timescales have shifted on the Pump House build. We now anticipate this starting in early 2026, rather than during Michaelmas term.
In the meantime, planned upgrades to the building fabric in Newnham Grange and Newnham Terrace will begin this term, to improve the insulation and energy efficiency of the site.