Stay up to date as the plans progress

27th April 2026

Today Darwin welcomed the first contractors on site, signalling the beginning of the Pump House building project.

The lead contractor, Barnes Construction, will have a permanent presence on site for the next year in order to coordinate the different teams and act as a point of contact for the College.

The full provisional programme is below, but over the first month the priorities will be to:
  • Prepare a contractor welfare area within the basement of 1 Newnham Terrace
  • Construct a flat-pack site office and run temporary services such as electricity to it
  • Remove the garden door from 1 Newnham Terrace garden door, replacing it with a temporary works door
  • Erect heras fencing around the work site and at the blue gates entrance
  • Clear the tank room (under the Dining Hall) and complete structural support works.
 The space under the Dining Hall will be the primary point of access for the contractors and their vehicles, so members and visitors are asked to exercise caution when entering and exciting the College via Newnham Road. Pedestrians and cyclists may be asked to wait while vehicles manoeuvre, to ensure safety.

27th February 2026
Final preparations have been made to the main site by the College teams ahead of the contractors’ expected arrival on site at the end of March.

A provisional schedule of works and impact to the main site can be seen below. This is wholly dependant on the progress of works and is subject to change. An updated version will be posted every month.

16th January 2026
In preparation for the building works to begin by the river, trees will be cleared next week behind 11 and 12 Newnham Terrace, as well as on the islands to provide clearance for punting.

29th September 2025
Owing to a delay in receiving the permissions required from the Environment Agency, timescales have shifted on the Pump House build. We now anticipate this starting in early 2026, rather than during Michaelmas term.

In the meantime, planned upgrades to the building fabric in Newnham Grange and Newnham Terrace will begin this term, to improve the insulation and energy efficiency of the site.

 

 

Timetable of works and their impact

2026 Pump House works / Building Fabric Works (in italics) / Major College garden events (in bold)
April & May Main contract site setup by contractor and river works commence

Transplant olive tree in pot to new location.

Remove rear door to 1 Newnham Terrace and replace with temporary workers’ door, install workers compound in the basement of 1 Newnham Terrace, install site office to the rear of 3 Newnham terrace and banksman’s office & skip to the front garden of 1 Newnham Terrace. Install skip to the front of 2 Newnham Terrace for College garden spoils to be recycled.

Blue gates to be closed and managed by banksman with no College vehicle access under the Hall.

Site compound segregated and Heras fencing erected.

Haul road excavation begins from under the Dining Hall / in front of the Cafe.

River wall platform and coffer dam construction begins via amphibious vehicles.

May Haul road and network trench, river wall working platform, site compound stripped

Working from the site compound at the rear of 12 Newnham Terrace towards the Dining Hall , excavating, laying network conduits in the trench then backfilling section by section. River wall works continue to establish working platform. Haul road continues to be backfilled and prepared for tarmac.

Coffer dam construction continues

Window, rooflight, and insulation replacement in Newnham Grange begins

May & June Haul road and preparation works continue

1st building connection trench begins to the Hermitage basement

Work on the new UKPN cabinet to the front of 9 Newnham Terrace begins

Works halted to allow for June Summer Event 27th June

July Haul road complete, piling begins

Haul road back-filling of the trench and tarmac

Site compound work begins: construction of pile matt and guide wall. Piling rig onsite.

Haul road used to bring in equipment, vehicles and remove spoils throughout the construction period.

July & August Pump House work continues in compound

Piling and Concrete works in the site compound continue

Garden parties and Graduation (marquee​​)

September  

Tail building (along pub wall) piling and concrete for foundations

Node connection to 12 Newnham Terrace

September  

Rayne Building (except Porters) closed and fully scaffolded and covered. Rayne offices temporarily relocated.

Newnham Grange student rooms closed 

Access to Newnham Grange offices and laundry to be via Laundry/Bridge doors and Deanery stairs

Rayne and Newnham Grange Ground floor corridor M&E trench works to be prioritised.

October Newnham Grange re-opens to residents for the academic year. 

Rayne to remain closed until Easter.

Tail building foundations completed.

Node connection to 11 Newnham Terrace

Node connection to 10 and 9 Newnham Terrace

Excavate drainage in Pump House

Rayne roof removed.

Graduation (marquee​​)

Node connection to 4,3,2 Newnham Terrace

November Rayne internal M&E works continue

Rayne Ground floor window and radiator works 

Work to North of Site along the path next to Newnham Grange, in the Bradfield Court and Punt sheds

 

↑ Top of the page

Impact on accommodation next year

The College recognises that residents living on the main site may be affected by the works to varying degrees.

Accommodation offers to both balloted continuing students and incoming new students will include information on the works and the disruption that may be caused. It has been agreed with the contractors that there will be fixed working hours (8am-6pm max) and no weekend working.

The College continues to offer alternative spaces for work and relaxing such as the Study Centre and the Reading Room. The Newnham Terrace properties closest to the construction site have been equipped with specially created study/common rooms.

↑ Top of the page

Related Sections